The existing bridge at the location was a timber bridge founded on timber piles, with timber abutments. The existing bridge was two spans, which was replaced with a single span prestressed concrete beam superstructure founded on driven steel piles and concrete abutments.
N/A
$228K
2017
Stahly Engineering assisted Fergus County in securing TSEP funds for the replacement of the bridge. Additional services provided by Stahly Engineering include:
This bridge is located over Big Spring Creek, and is in a detailed flood study area, meaning the water surface of the creek could not be increased at all. In addition, lengthening the bridge to accommodate hydraulics was a challenge due to the proximity to the highway on the east, and a residential driveway on the west.